Temporary electricity connection for
house construction in Bangalore.

Everything you need to know before your build starts — timeline, cost, documents, and what happens when construction ends.

Why you need one

Any independent house construction site in Bangalore needs power for mixers, drills, welding, lighting, and — critically — curing (keeping concrete wet as it sets, which often needs pumped water and lighting over several weeks). Running all of this off a diesel generator for months is expensive, noisy, and draws complaints from neighbours. A temporary BESCOM connection is the legal, practical way to get grid power to a site that doesn't have a permanent connection yet.

What the process looks like

A temporary connection follows a similar shape to a new connection, but sized and priced for short-term use:

  • Application with load estimateYou (or your contractor) estimate the load needed for construction equipment — mixers, drills, site lighting — and apply for a single-phase or three-phase temporary connection accordingly.
  • Site inspectionBESCOM verifies the site is ready for a temporary meter connection — access, safety, and load matching the application.
  • Deposit & sanctionA refundable deposit is paid based on the sanctioned load, and the connection is officially sanctioned.
  • Meter installationA temporary meter is installed at the site, and power is live.

Timeline and validity

Expect 10–20 working days from application to meter installation, depending on load size and how quickly the site is ready for inspection. Temporary connections are typically sanctioned for 6 months and can be extended if construction runs longer — worth planning for if your build timeline is tight.

Tariff — the part people forget

Temporary connections are billed at a higher per-unit tariff than a standard residential connection. It's a fair trade during construction, but it's a good reason not to leave the temporary connection running longer than necessary once the house is livable — converting to permanent sooner rather than later saves money.

What happens when construction ends

Two paths, both handled through BESCOM: the temporary connection is officially disconnected and your deposit is refunded, or — more commonly for a house you're going to live in — it's converted to a permanent residential connection. Conversion is usually simpler than applying fresh, since BESCOM already has the site and load details on record.

Documents to keep ready

  • Site ownership proofSale deed or khata for the plot.
  • Approved building planSanctioned plan from BBMP/BDA or the relevant authority.
  • ID and address proofAadhaar or PAN, plus a current address for correspondence.
Where a contractor actually saves you time

The load estimate and inspection scheduling are where most delays happen — an under-estimated load means a second round-trip. We size the application correctly the first time and handle every BESCOM step, including the eventual conversion to permanent. See our Temporary Connection service for the full details.

Frequently asked

Quick answers

A temporary BESCOM connection is safer, cheaper to run for sustained use (mixers, drills, curing, lighting over months), and avoids fuel logistics and generator noise complaints. It's also the only legal way to draw grid power at a site that doesn't have a permanent connection yet.
Typically 10–20 working days from application to meter installation, depending on load requirement and how quickly the site is ready for inspection.
Yes. Once construction is complete, the temporary connection can be converted to a permanent residential connection, usually with a simpler process than starting from scratch since BESCOM already has your site on record.
Yes — temporary connections carry a higher per-unit tariff than a standard residential connection. It's worth converting to permanent as soon as your building is livable rather than running on temporary tariff longer than needed.